 Work In Progress
   start 10th floor on 1 Sep 2008  
 
 
   Start 8th floor on 15 Aug 2008  
 
 
   The 6th floor has compleated on 29 July,2008  
 
 
   Start 5th floor on July 16,2008  
 
 
   Start 3rd floor on June 28, 2008  
 
 
   Start 2nd floor June15,2008  
 
 
   Birds Eye View Constrution June 01, 2008  
 
 
   Start of Main building constrution May 2008  
 
 
   Footing work completion-April 2008  
 
 
   Feb- March 2008 Footing continues  
 
 
   1st line footing on Jan 2008  
 
 
   Piling - Dec 2007  
 
 
   Stress Test August 2007  
 
 
   Preparation for Stress Test July 2007