| Work In Progress |
| |
start 10th floor on 1 Sep 2008 |
|
| |
|
|
| |
Start 8th floor on 15 Aug 2008 |
|
| |
|
|
| |
The 6th floor has compleated on 29 July,2008 |
|
| |
|
|
| |
Start 5th floor on July 16,2008 |
|
| |
|
|
| |
Start 3rd floor on June 28, 2008 |
|
| |
|
|
| |
Start 2nd floor June15,2008 |
|
| |
|
|
| |
Birds Eye View Constrution June 01, 2008 |
|
| |
|
|
| |
Start of Main building constrution May 2008 |
|
| |
|
|
| |
Footing work completion-April 2008 |
|
| |
|
|
| |
Feb- March 2008 Footing continues |
|
| |
|
|
| |
1st line footing on Jan 2008 |
|
| |
|
|
| |
Piling - Dec 2007 |
|
| |
|
|
| |
Stress Test August 2007 |
|
| |
|
|
| |
Preparation for Stress Test July 2007 |
|
| |
|
|